The sand and dust tester, also known as the sand and dust test box, is mainly used for conducting dust tests on electrical, electronic, household appliances, car lights, motorcycles, chemical and other components and materials, in order to test the sealing performance of the product's shell and meet the GB4208-93 shell protection level IP5X/IP6X dust test. The sand and dust tester is mainly used to simulate the damage caused by sandstorms to locks, automotive and motorcycle components, seals, and electrical instrument lights.
Below, the technical editor of Dongguan Aisili Testing Equipment Co., Ltd. will provide you with a detailed introduction to the correct operating procedures for the sand and dust tester:
1、 Safe operation and basic precautions of sand and dust tester
1. The test medium must not contain any items or components that do not meet the requirements.
2. After the experiment is completed, if the device is not turned on for a short period of time, the test medium should be removed and the box should be wiped dry to maintain cleanliness.
3. When taking the medium, open the seal under the bottom pipe of the inner container and then close it. It is recommended to use a vacuum cleaner to remove the remaining dust.
4. Due to the fact that the box door is made of glass, the closing and opening of the box door should be done gently and gently, and prevent heavy impact on the box door.
5. Prohibit testing explosive, flammable, and highly corrosive substances.
6. The test medium cannot be used more than 20 times.
7. Chemical drugs are prohibited from coming into contact with this equipment to avoid external impact.
2、 Before the operation of the sand and dust tester
1. The operator must understand the structure and performance of the system, as well as the cleanliness and lubrication of the equipment, proficiently master the operation process of the equipment, and pass the examination before using the equipment.
2. Check that the rated voltage of the device is three-phase 380V. If the external voltage is unstable, a stabilized power supply must be prepared.
3. Before each startup, check the circuit control system to ensure reliable grounding of the equipment.
3、 During the operation of the sand and dust tester
1. Open the box door, put the test medium (such as talcum powder, etc.) into the box, and close the box door. Connect the power supply, turn on the power switch, set various test methods (such as lighting, heating, blowing dust, vibration), and set the desired temperature on the temperature controller.
2. Observe whether the circulating fan is operating normally.
3. Observe whether the vibration of the vibration motor is normal, and make the vibration motor impact the hopper to promote the circulation of the test medium.
4. If the no-load test machine is normal, the test medium can be placed in the hopper at the bottom of the working room according to the standard requirements.
4、 After the sand and dust tester works
1. After the experiment is completed, cut off the power supply of the entire machine.
2. The operator should take out the test sample after a period of time, as the box is filled with dust and may cause injury to the operator. After the dust settles, the item should be taken out.
3. After cutting off the power, the operator must conduct a comprehensive inspection of the machine.
4. The operator should carefully clean the test chamber and maintain a dry environment inside.