At the customer site of a pharmaceutical factory in Songjiang, Shanghai, it has been running continuously for three months, with good operating conditions and high customer satisfaction!
Weekly operation and maintenance are to safeguard the equipment, and precise numerical values are to provide customers with safety and peace of mind!

Construction of monitoring substation building
Monitoring sub station buildings should be monitored as much as possiblechoicebuilt inNear the sample source (discharge outlet or channel) to reduce analysis latency.
Monitor the area of the substation buildingnot less than15 m2.The ground where the instrument is placed should be tiledThe ground is required to be flat and level, corrosion-resistant, and vibration free. The instrument ground should be at least 300mm higher than the sampling port ground to ensure that there are no protrusions or depressions in the middle of the pipeline.
On the wall near the sewage channel in the monitoring substation buildingShould be based onRequest to open corresponding holes and pre lay the required pipelines.
Pump selection
The power of the water pump that delivers water samples from the sampling point to the instrument should be such that the flow rate of the measured water to the instrument is not less than50rise/minute, not greater than200rise/Minutes are appropriate. Usually, the distance between the sampling point and the instrument is less than20When selecting rice, choose350WThe submersible pump. When the distance between the sampling point and the instrument is greater than20When it comes to rice, it should be selected550-750WThe submersible pump should also consider whether to choose a corrosion-resistant pump based on the corrosiveness of the water sample.
Layout of pumps and pipelines
The water pump, conduit, water sample inlet pipe, outlet pipe, and overflow pipe should be pre installed from the sampling point to the instrument installation location. The connected pipes should be made of rigid polyvinyl chloride plastic according to the specific situationABSHard pipes made of engineering plastics or steel (metal pipes cannot be used in areas with acidic or alkaline water), stainless steel, and other materials. For the convenience of connecting with instruments and equipment, it is recommended to use hard pipesPVCManage.