Component testing device for respiratory and drainage devices
1Overview:
Respiratory and drainage devices are based onGB/T 3836.2-2021Explosive Environment2part:Made of explosion-proof shell“d'Protected Equipment10.9.3After the bubble test,asExThe breathing and drainage device of the component should withstand a thermal test at the specified maximum volume of the explosion-proof shell, as shown in the usage diagram21In the case of the experimental device, the maximum volume is2.5LThe left and right regulations stipulate that multi-purpose breathing and drainage devices used for any single explosion-proof enclosure should be tested together with the enclosure.
2、 Key pointparameter:
parameter item |
Specifications |
control system |
PLC+Windows |
operating interface |
15Inch industrial control all-in-one computer |
test software |
Our company's self-made |
total length |
≥2174mm |
Experimental pipe section |
4Paragraphs, each paragraph500mm |
Wall tube thickness |
≥6 mm |
Test pressure |
≥6MPaAccuracy: ±2.5% |
|
Sample installation foundation section
|
Inner diameter ≥275mm, Length>174mm |
exhaust vent |
≥1One, manual exhaust valve |
Ignite the mouth |
≥3a |
temperature sensor |
SType temperature sensor |
power supply |
AC220V 50Hz |
IIIexecuteStandards and Applicable Scenarios
Execution standard:
GB/T 3836.2-2021Explosive Environment2part:Made of explosion-proof shell“d'Protected Equipment
Test Procedure
1)The ignition source should be located at the entrance of the casing,And it is located on the inner side of the end plate that accommodates the device50mm,Observation results
2)When applicable, the test mixture should be in accordance with the standard15.4.3.1Preparation of regulations
3)During the experiment, the external surface temperature of the device should be monitored
4)Any device should be operated in accordance with the manufacturer's documentation. In5After each test, the explosive mixture should be kept outside the device for a sufficient period of time, at least10min,Allow continuous combustion on the surface of the device to a significant degree, causing an increase in temperature on the outer surface of the device or enabling temperature to be transmitted to the outer surface.
5)For each gas mixture of the specified gas category used in the device,The experiment should be conducted5Next time.
Configuration List
host1Taiwan;
Instruction Manual1copy;
Certificate of Conformity1copy;
Warranty Card1copy;
Delivery Receipt1copy;
nameplate1block;
power cord1root;
wrench1set;
Several brochures;